Project timeline and progress

  • 5-19 Dec (14 days) : Define required data parameters
  • 19 Dec – 5 Jan (17 days) : Document literature search methodology and record new datasets
  • 5-24 Jan (19 days) : Pre-process input data for carbon budget modelling
  • 24 Jan – 12 Feb (19 days) : Conduct forest carbon simulations
  • 12 Feb – 3 Mar (19 days) : Document results and publish a case study

I’m currently fitting different tree species’ growth curves collected from research papers, using scipy optimize and Excel Solver. I should be able to run a simulation soon.

Just for fun, I created a little interactive web app for visualizing what the parameters do during curve fitting.

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: